Villages cleared, river diversion work underway at China’s Medog dam project in Tibet

Must read

- Advertisement -spot_img

Tenzin Nyidon 

DHARAMSHALA, Nov. 27: Fresh satellite imagery of China’s massive Medog hydropower project on the Yarlung Tsangpo River in occupied Tibet shows entire villages and agricultural land cleared, new access roads constructed and possible river diversion works underway, raising renewed concerns over the world’s largest hydropower project’s environmental and social consequences.

The findings are contained in an 18-page assessment titled Building at the Great Bend: Monitoring China’s 60 GW Medog Dam Project, released by EarthSense Labs, an Indian geospatial artificial intelligence (AI) start-up incubated at the Foundation for Innovation and Technology Transfer (FITT), Indian Institute of Technology (IIT) Delhi. 

The assessment, based on satellite imagery collected over several years, documents extensive construction activity at multiple locations associated with the proposed project. According to the report, satellite imagery taken on July 11, 2025, before the project’s official groundbreaking ceremony, showed villages and agricultural fields along the southern bank of the river near the proposed main dam site at Mainling. By December 4, 2025, the settlements and agricultural fields had been cleared, with earthworks visible in the area.

The project, formally launched by China in July 2025, is planned as a cascade system comprising five hydropower stations along the lower reaches of the Yarlung Tsangpo. With a proposed installed capacity of 60,000 megawatts (60 GW), it is expected to become the world’s largest hydropower project, with an estimated investment of 1.2 trillion yuan, approximately US$168 billion.

EarthSense Labs’ assessment identifies four major locations associated with the proposed hydropower infrastructure: a main dam near Mainling, a possible lower dam near Pai town, a proposed tunnel through the Namcha Barwa mountain massif, and a tunnel outlet and construction zone downstream of Medog County, close to the Indian border.

The latest findings have renewed questions about the impact of the project on Tibetan communities in occupied Tibet. The apparent clearance of settlements and agricultural land raises questions about the fate of residents, the scale of displacement, the relocation process and whether affected communities were adequately consulted or compensated. The satellite assessment documents physical changes to settlements and land use but does not establish the number of people displaced or the circumstances surrounding their relocation.

The project’s location near the seismic zone has also prompted concerns about the risks associated with large hydropower infrastructure in an earthquake-prone region. The scale of the proposed tunnel network and the alteration of river flows warrant close scrutiny, particularly given the limited availability of independently verifiable environmental information.

The Yarlung Tsangpo, which originates in occupied Tibet, enters India’s Arunachal Pradesh state as the Siang and subsequently flows through Assam as the Brahmaputra. The scale and location of China’s project have raised concerns in India over downstream water security, possible changes in seasonal river flows, sediment transport and the potential consequences of sudden water releases.

Beijing has maintained that the project will generate electricity without significantly affecting downstream water availability. However, the absence of a comprehensive and binding water-sharing agreement between China and India has continued to fuel concerns over transparency and access to information about upstream infrastructure.

In response to the strategic and water-security implications, India has proposed the 11,200 MW Siang Upper Multipurpose Project in Arunachal Pradesh, which officials say could help regulate downstream flows. However, the project has faced growing opposition from local communities, including through the anti-dam movement, with residents raising concerns over displacement, environmental damage, the loss of traditional livelihoods and the potential submergence of villages and ancestral lands.